A Honey Bee Swarm Optimization Algorithm for Minimizing the Total Costs of Resources in MRCPSP


Affiliations
1 Department of Industrial Engineering, Science and Research Branch, Islamic Azad University, Tehran, Iran, Islamic Republic of
 

In this paper, we introduce a multimode resource-constrained project scheduling problem with finish-to-start precedence relations among project activities, considering renewable and nonrenewable resource costs. We assume that renewable resources are rented and are not available in all periods of time of the project. In other words, there is a mandated ready date as well as a due date for each renewable resource type so that no resource is used before its ready date. However, the resources are permitted to be used after their due dates by paying penalty costs. The objective is to minimize the total costs of both renewable and nonrenewable resource usage. This problem is called multi-mode resource-constrained project scheduling problem with minimization the net present value of total weighted resource tardiness penalty cost (MRCPSP-DCTWRTPC) where for each activity, both renewable and nonrenewable resource requirements depend on activity mode. For this problem, we present a meta-heuristic algorithm based on a Honey Bee Swarm Optimization (HBSO) approach together with a prioritization rule for activities and several improvement and local search methods. Experimental results reveal the effectiveness and efficiency of the proposed algorithm for the problem in question.

Keywords

Honey Bee Swarm Optimization, Multi Modes, Project Scheduling, Resource Cost; Tardiness Penalty Cost
User

Abstract Views: 197

PDF Views: 0




  • A Honey Bee Swarm Optimization Algorithm for Minimizing the Total Costs of Resources in MRCPSP

Abstract Views: 197  |  PDF Views: 0

Authors

Mohammad Khalilzadeh
Department of Industrial Engineering, Science and Research Branch, Islamic Azad University, Tehran, Iran, Islamic Republic of

Abstract


In this paper, we introduce a multimode resource-constrained project scheduling problem with finish-to-start precedence relations among project activities, considering renewable and nonrenewable resource costs. We assume that renewable resources are rented and are not available in all periods of time of the project. In other words, there is a mandated ready date as well as a due date for each renewable resource type so that no resource is used before its ready date. However, the resources are permitted to be used after their due dates by paying penalty costs. The objective is to minimize the total costs of both renewable and nonrenewable resource usage. This problem is called multi-mode resource-constrained project scheduling problem with minimization the net present value of total weighted resource tardiness penalty cost (MRCPSP-DCTWRTPC) where for each activity, both renewable and nonrenewable resource requirements depend on activity mode. For this problem, we present a meta-heuristic algorithm based on a Honey Bee Swarm Optimization (HBSO) approach together with a prioritization rule for activities and several improvement and local search methods. Experimental results reveal the effectiveness and efficiency of the proposed algorithm for the problem in question.