Black Start Mock Drill from Pench Hydro Power Station in Madhya Pradesh for Khaparkheda Thermal Power Station in Maharashtra, India


Affiliations
1 Area Load Despatch Center, 8th Mile, Amravati Road, Wadi, Nagpur – 440023, Maharashtra, India
     

   Subscribe/Renew Journal


The periodic testing and validation of grid recovery procedures are mandated by The Indian Electricity Grid Code (IEGC) 20105, which includes Black start procedure for total/partial blackouts and re-synchronization of Island and this procedures needs to practiced at-least twice a year. Black Start mock drills are carried out to learn the behavior of the system while recovering from total/partial blackouts and from such mock drills the engineers will be able to figure out the challenges and responses of the equipment’s at different stages of the procedure. Pench Hydro Power Station is the only Hydro Power Station available nearby and there is no gas generation available in the vicinity of Nagpur district of Maharashtra, India. And Thermal generation available around area is 10000 MW. This paper is the experience about carrying out black start mock drill for 220 kV Khaparkheda Thermal power station from Pench Hydro Power Station and synchronizing of Small Island with national grid created during the mock drill.

Keywords

Black Start Mock Drill, Grid Recovery Procedure, Khaparkheda Thermal Power Station, Pench Hydro Power
User
Subscription Login to verify subscription
Notifications
Font Size

  • Mukhopadhyay P, Pandey V, Das AP, Kumar C, Bende PAR, Prabhakar KK, et al. Black start experiences for 400 kV hydro power plant In Western Regional Grid of India. 2016 National Power Systems Conference (NPSC). 2016. https://doi.org/10.1109/NPSC.2016.7858948
  • Gartia A, Pandey V, Das AP, Prajapati PK. Black start exerciseexperience and learning over past 7 years in Western Region, India.
  • Raoot MG, Pentayya P, Mishra S, Patel H. Blackstart restoration plans for western region and case studies. Fifteenth National Power Systems Conference (NPSC),IIT Bombay; 2008.
  • Central Electricity Authority, All India installed capacity [Internet]. Available from: https://cea.nic.in/installed-capacityreport/?lang=en
  • Indian Electricity Grid Code [Internet]. 2010. Available from: https://cercind.gov.in/2016/regulation/9.pdf 6. Maharashtra Electricity Regulatory Commission [MERC] state grid code [Internet]. 2020. Available from: https://www.merc.gov.in/faces/merc/common/outputClient.xhtml
  • Maharashtra State Load Despatch Center, daily report [Internet]. Available from: https://mahasldc.in/home.php/daily-reports/
  • Maharashtra State Power Generation Co. Ltd. Installed Capacity [Internet]. Available from: https://mahagenco.in/index.php/generation

Abstract Views: 79

PDF Views: 0




  • Black Start Mock Drill from Pench Hydro Power Station in Madhya Pradesh for Khaparkheda Thermal Power Station in Maharashtra, India

Abstract Views: 79  |  PDF Views: 0

Authors

Bhaurao T. Raut
Area Load Despatch Center, 8th Mile, Amravati Road, Wadi, Nagpur – 440023, Maharashtra, India
Arvind B. Dadmal
Area Load Despatch Center, 8th Mile, Amravati Road, Wadi, Nagpur – 440023, Maharashtra, India
Rajendra S. Vekhande
Area Load Despatch Center, 8th Mile, Amravati Road, Wadi, Nagpur – 440023, Maharashtra, India
Pankaj M. Shinde
Area Load Despatch Center, 8th Mile, Amravati Road, Wadi, Nagpur – 440023, Maharashtra, India
Sachin P. Pendor
Area Load Despatch Center, 8th Mile, Amravati Road, Wadi, Nagpur – 440023, Maharashtra, India
Nishant Harjal
Area Load Despatch Center, 8th Mile, Amravati Road, Wadi, Nagpur – 440023, Maharashtra, India

Abstract


The periodic testing and validation of grid recovery procedures are mandated by The Indian Electricity Grid Code (IEGC) 20105, which includes Black start procedure for total/partial blackouts and re-synchronization of Island and this procedures needs to practiced at-least twice a year. Black Start mock drills are carried out to learn the behavior of the system while recovering from total/partial blackouts and from such mock drills the engineers will be able to figure out the challenges and responses of the equipment’s at different stages of the procedure. Pench Hydro Power Station is the only Hydro Power Station available nearby and there is no gas generation available in the vicinity of Nagpur district of Maharashtra, India. And Thermal generation available around area is 10000 MW. This paper is the experience about carrying out black start mock drill for 220 kV Khaparkheda Thermal power station from Pench Hydro Power Station and synchronizing of Small Island with national grid created during the mock drill.

Keywords


Black Start Mock Drill, Grid Recovery Procedure, Khaparkheda Thermal Power Station, Pench Hydro Power